Application Case
Project: Tongmei Datang Tashan Coal Mine Total Automatic Control System
Customer: Datong Coal Group
Location: Datong, Shanxi Province
General Description: Tongmei Tashan coal mine with designed production capability 1.5Mt/a
is the largest coal mine in China. The construction started in 2004 and it started normal operation
in 2007. Honeywell coal mine automation system was deployed in Tashan. System engineering
started in Oct. 2006 and system started to operate in January 2007. System provides safety
monitoring, production monitoring, and management function with Fault Tolerant Ethernet. All
underground and surface production process can be monitored. Realtime data collection, transmission,
processing, display, and print can be achieved and this ensures the equipment and people¡¯s safety.
Scope of Honeywell Supply: Safety monitoring, power supply monitoring, traffic tracking, equipment
monitoring, pump station monitoring, people tracking, coal face monitoring, coal preparation monitoring,
conveyer system monitoring, and control system platform
System Configuration: Experion PKS system platform, FTE network, C200 control substation, eServer
information issue, DVM video monitoring
Control Function: CH4 interlock with wind and power, coal Conveyor monitoring, power monitoring,
pump station and Longwall monitoring